We started this High Springs custom home for my clients just before Thanksgiving, and worked to complete the foundation, frame the walls, set the trusses, deck the roof, and dry in the house all before the Christmas holiday. I'm going to outline the steps along with progress pictures we took during the first month of construction
Foundation:
- We started by bringing in clean fill dirt & leveling & compacting the pad
- Then w
Framing:
- Exterior Walls
- Interior Walls
- Wall Sheathing
- Set Trusses
- Deck Roof
- Dry-In